|
1
|
- Energy Reduction
- Cost-effectiveness of Process Simulation and Pinch analysis
- Chris Connaghan, P.Eng., Duncan Industrial
- Gaétan Noël, M.Sc. Eng., Pragmathic
- Larry Wasik, P. Eng., Aurel Systems
|
|
2
|
- Often heard reasons for lack of interest:
- Too expensive: it generates no savings by itself and has no payback !
- We do not need that, we already know what to do ...
- Energy efficiency is often not profitable, paybacks are always much
longer than the studies indicate !
- Our processes change continuously, any study results will only be valid
over a few months period
- As a consequence, payback of installed projects takes longer
|
|
3
|
- Mills are complex with many interrelated systems
- Energy savings in one department may simply cause additional energy
usage in another department
- Improving energy efficiency in a major way needs a dedicated approach
- This approach is Computer Simulation and Pinch analysis
- Many case studies can now show the benefits of this expertise
|
|
4
|
- It is now possible to simulate a complex integrated mill with a single
computer simulation
- The energy saving of a given project can be determined rigorously
- all interactions between the different components of the process are
taken into account by the simulation
- high level of confidence for the predicted energy savings
|
|
5
|
|
|
6
|
- Precise information provided by the process simulation
- It gives information on the energy efficiencies of your processes,
equipments and unit operations
- It allows the identification of problems that can often be easily and
cheaply solved
- The approach and thinking process governing the streams selection for
the Pinch analysis study generates many profitable findings
|
|
7
|
- In consequence, the study itself has its own payback
- Short payback of a few months
- Based on the authors’ experience, there has been no exception to this
rule so far for any mill
|
|
8
|
- The process simulation has shown:
- Severe fouling of the heat exchanger used for effluent cooling by
energy recovery
|
|
9
|
- The process simulation has shown:
- Severe fouling of the TMP reboiler
- Reboiler retubing has been done
|
|
10
|
- From the Pinch Analysis streams data extraction phase:
- Fresh water can be displaced by ww for the chips impregnation on TMP
lines 1 and 2
- •savings around 200k$/yr
- • very cheap project
- • refunds the study
- within a few months
|
|
11
|
- From the Pinch analysis streams data extraction phase:
- Excess pressurized contaminated TMP steam from any of the 3 lines can
be sent into
- the chip bins of any other
- line when fresh steam is
- consumed
- Savings around 650 k$/yr
- with a very small payback
- Precise contaminated
- steam balance helps greatly
- to catch these opportunities
|
|
12
|
- From the Pinch Analysis streams data extraction phase:
- Possible to recycle a
- reclaim screen effluent
- to the chip washer
- Confirmed with the process simulation
- Very cheap modification
- with savings around
- 150 k$/yr
|
|
13
|
- Example 6: TMP clear ww cooling by energy recovery: air preheating of
the pulp flash dryers
- The following project had been submitted to management
- Savings given were around 780 k$/yr
- Anticipated payback of 13 months
|
|
14
|
- Process simulation shows that only 25% of estimated savings would happen
- Cooler ww means less steam generated by the refiners
- Cooler ww reduces the existing amount of energy already recovered from
the TMP
- Now the corrected payback requires 52 months instead of 13 months !!
- This is an example where a waste of capital can be avoided
|
|
15
|
- Question: what is the minimum ww temperature that can be set with no
penalty to the energy recovery potential ?
- Pinch Analysis can answer such a difficult question using composite
curves
- Capital cost can even be
- assessed ahead of
- any design!!
|
|
16
|
- Pinch Analysis can then be used to correctly identify the profitable
options to cool ww
- With the correct evaluation of the savings using the computer simulation
- The computer simulation output is used to modify the streams’ data set
used for the Pinch analysis
|
|
17
|
- Computer Simulation is used to modify the streams’ data set for the
Pinch Analysis
|
|
18
|
- Example 7: TMP Pulp Mill in BC
- Steam boiler feedwater preheating often on the wish list of all mills
- What about if you can shut the boiler off 1 or reduce its
load drastically within a 1 yr payback ?
- Pinch analysis and computer simulation can avoid a waste of capital
expenditure
- Note 1 : Obviously, not all mills can afford to shut all the boilers
off because of process constraints
|
|
19
|
- Example 7: TMP Pulp Mill in BC
|
|
20
|
- Example 8: Kraft Mill in Qc
- Large flowrate of cold ClO2 solution used for the bleaching
- Mill’s suggestion: heat the solution with some hot condensate
- Composite curves show this is a non-optimal choice
|
|
21
|
- Example 9: TMP Mill in Qc
- Target: cool the effluent to 37 deg. C
- Composite curves show this is impossible with the current operating
conditions
|
|
22
|
- Option: consider judicious process modifications
- To achieve that correctly,
- Process Simulation is mandatory
- Solution: increase temperature
- set point of the TMP ww network
- to 76°C
|
|
23
|
- You may think that some of the previous examples are very simple,
obvious and easy to identify projects, but remember that...
- A well done job using rigorous approaches often delivers crystal clear
solutions that follow the KISS rule: Keep It Simple Stupid
- This is a usual consequence of Pinch Analysis and Computer Simulation
|
|
24
|
- Major changes frequently occur and can impact the selected projects of an energy
efficiency program
- A possible approach: include some flexibility in your plan of action
- A few alternate solutions from Pinch Analysis design rules can be found
for a given selected value of dTmin
- This gives options to the mill and add some flexibility to the solutions
presented
|
|
25
|
- Ex. 10 (QRP): ww heating for the bleaching: 2 options
|
|
26
|
- ... leading to a flexible road map of (as much as possible) independent
projects
|
|
27
|
- Computer Simulation and Pinch Analysis have come of age
- Now it is possible to simulate complex integrated mills in a single
simulation
- Energy saving projects identified the conventional way cannot bring the
mill to its maximum energy efficiency potential and can lead to some
waste of capital
- With the existing trend resulting from the Greenhouse gases concerns and
the Kyoto protocol, this approach is a powerful tool available to
minimize a mill’s CO2
emissions in a profitable economic context
|