Notes
Slide Show
Outline
1
CSChE 2002, Thermal Pinch Analysis
  • Case Study
  • TMP Pulp Mill Process Simulation and
    Pinch Analysis Results


  • Chris Connaghan, P.Eng., Duncan Industrial
  • Mike Van Aert, P. Eng., Quesnel River Pulp
  • Gaétan Noël, M.Sc. Eng., Pragmathic
2
Quesnel River Pulp Mill
Quesnel, BC
  • Bleached TMP pulp mill
    • 930 ADMT/D
    • 3 lines of refining totalling 118,000 HP or 88 MW
    • 3 flash dryers

3
Quesnel River Pulp Mill
Quesnel, BC
  • Thermal Energy System Description:
    • Natural gas used for:
      Package Steam Boiler
      Glycol Boiler
      Pulp Flash Dryers
    • Reboiler converts Refiner Dirty Steam to Clean Steam
    • Glycol Heat Exchangers preheats Glycol using Dirty Steam
    • Glycol heats Air Supply for Flash Dryers
    • Effluent Heat Exchangers recover Waste Heat





    • Fossil fuel: natural gas @ $5.00/GJ HHV
4
Mandate and Methodology
  • Mandate:
    • Reduce mill effluent temperature and volume
      Maximize energy savings with two year payback or less
  • Methodology:
    • Mill Wide Cadsim+ Computer Simulation
      Extensive Onsite Verification of Computer Simulation
      Identify Energy Conservation Opportunities to reduce effluent temperature and volume
    • Pinch Analysis to Identify & Optimize additional ECO ’s
5
Mandate and Methodology (end)
  • Study started fall 2000,
        completed spring 2001
  • Immediate Project Implementation by the mill
    with no delay
    • Some projects even started during the study
6
Process Simulation (1)
PreSteaming Bins, Impreg  Tower
  • Detailed balances done by Duncan Industrial using Cadsim+
7
Process Simulation (2)
Refiners and Cyclone
8
Process Simulation (3)
White Water Chests
9
Process Simulation (4)
  • Major effort put on data collection, measurements and model validation
  • Strong process knowledge and simulation expertise required to build the simulation
    • correct choice of simulation building blocks and specifications to produce reliable predictions when modifications are evaluated
    • Requires an experienced engineer understanding mill process and simulation
      • Cadsim+ may look like but is not a computer game
10
Process Simulation (end)
  • Computer Simulation Identified:
    • Effluent cooling heat exchangers severly fouled
      25% of design heat transfer, cleaned by the mill
    • TMP reboiler capacity lost
      Severe shell-side tube fouling with no access for cleaning
      Retubed with 20% more heat exchange area
      40% more clean steam production
      Therefore, less steam from gas package boiler
    • Boiler feed water preheating
      Heat exchanger ordered immediately
11
Pinch Analysis:
Data extraction
  • Pinch analysis done by Pragmathic
  • Stream data from the computer simulation
12
Pinch Analysis:
Operating Scenarios
13
Pinch Analysis:
Parameters for Cost Estimating
14
Pinch Analysis Energy targeting
15
Pinch Analysis Targets
  • Reliable TARGETS, dTmin = 20°C
  • Final solution designed for 26% savings in natural gas
16
Process Improvements Identified from Pinch Analysis
  • Increase reboiler’s production:
    • Increase size of blow lines, reduce quench water flowrate;
    • From mill / simulation: reboiler maintenance/rebuilt
  • Increase operating temperatures of:
    • the glycol loop
    • impregnator
    • chips' washing system
    • dewatering process temperature
    • refiners’ dilution and shower water
  • Replace the fresh water with clear white water:
    • impregnators
    • refiners’ dilution and shower water
17
Energy Saving Projects - 1
18
Energy Saving Projects - 2
19
Energy Saving Projects - 3
20
Energy Saving Project
 Summary
21
Action Plan
  • Flexible road map
  • Step 1: Implement Projects in any order as you wish:
    • Maximum savings target = 13900 kW minus new additional reboiler’s capacity
      • In fact, the rebuilt reboiler has a 40% larger production rate
    • Flexible solution adaptable to the mill’s changing context
  • Step 2: update energy balance and check actual results
  • Step 3: update study and implement other projects if some potential is still there
22
Projects Implemented (1)
  • Reboiler rebuilt
  • Recover excess refiners’ steam for chips bins
  • Impregnation fresh water displaced by ww (lines 1&2)
  • Increased glycol loop heating with excess refiners atmospheric steam
    • Capacity of existing atm. steam condensors has been increased
      • Fan malfunction identified and repaired during the study course
23




Projects Implemented (end)
  • One effluent HEX installed (part of P4B)
  • Boiler feedwater preheater installed
    • Not used with steam boiler shut-off normally
    • Still generates profitable savings for the other operating scenarios
  • During winter 2001, both steam and glycol boilers were off during normal production
24
Reboiler Modifications
25
Boiler Feedwater Preheating
26
Effluent Cooling Exchangers
27
Natural Gas Savings and
 Green House Gas Reduction
28
Fresh Water Savings
29
Economic Results to Date...
  • Payback well below 1 year. Savings equal to  35% of the  total gas bill
30
Conclusions
  • Outstanding results in a short period of time as a consequence of:
    • Rigorous and « precise » methodology
    • Clear study recommendations
    • Mill ’s personnel and management willingness


  • Energy / Process integration using computer simulation and Pinch Analysis is the most cost-effective approach to maximize savings and beneficial environmental effects (GHG, fresh water usage)
    • But needs experienced and practical engineers
    • Very important to listen to the mill’s personnel and incorporate their ideas in the studying process